Work needed to Raise Great Pyramid, Tier-by-Tier
Numbers of Men Directly Employed in Hands-On Work
Rates of Setting Stone in Place
Rates of Setting Stone during corvée
![]()
If you look up any good book on the pyramids it will give you basic information on each pyramid's height, base lengths, volume, weight, orientation, etc. For instance, the Great Pyramid has a volume of 2,583,283 cubic metres, height 146.59 metres, base of 230.33 metres, a mass of 7 million tonnes, and so on.
Using these figures, it is possible to work out other factors like the rate of laying stones, in tonnes per hour, given a build time generally assumed for the Great Pyramid to be 20 years. The figure often quoted is 89 tonnes per hour, which would be an average over the full 20 years - pretty tremendous, but does the average conceal even higher peak rates?
Such average figures can be quite misleading, especially when you realize that putting the top stones in place must have taken a lot more work than putting on a base stone, which did not have to be raised up the pyramid.
And that's another issue. How were the stones raised? Up some ramp, as is often widely assumed? If so, what slope would the ramp have had, and how many stones per hour were being hauled up this ramp at peak against the friction forces of wooden sledges being hauled over rough surfaces? Or, were the stones raised some other way, not involving the heavy workload of overcoming friction?
It turns out that these kinds of questions can be answered quite sensibly by simple calculations - not of the averaging kind above, but as follows:
- How many men for each tier
- How long each tier took
- How much food and beer were needed
- How many ovens and vats would be needed and how many people would be needed to carry food and water, bake bread and brew beer.
- How many boats would be needed to supply the grain and water
The point of separating the calculations into tiers then, is that, instead of being stuck with averages, we can see how the building must have progressed over time. By using a simulation calculator, we can apply sensitivity checks, so that initial asumptions about times, levels of effort, diets, etc., can be varied separately and together to produce robust, statistically sound answers.
But, a word of caution. Using physics as a basis for working things out tends to provide an underestimate. There are so many things for which basic physics does not allow, e.g. waiting around time, supervision, organization, shiftworking, etc. Additionally, physics would not be useful for working out the mapower involved in stone carving, polishing, etc.
Physics, then, since it results in an underestimate of manpower and effort, cannot prove any theories to be correct, but it can certainly prove some theories to be incorrect.
![]()
The figure shows some of the numerical values used in calculating the work assoociated with raising the Great Pyramid. The bulk of the stone was quarried on the Giza plateau, some 350m away and, while there may be doubts about a ramp on the Pyramid, it seems clear that a ramp was used to haul stone from the quarry to the base of the Pyramid.
The following graph shows the calculated work needed to raise each tier, measured in Joules.
There are 3 lines on the graph:-
There was more to any pyramid complex than the pyramid. Additionally, calculations must account for:
The following graph shows the work needed for some of the features associated with Khufu.
The graph uses the tier number as the X-axis, rather than time in years. The amount of work per tier spent on the Causeway is a variable, since the calculator can be set to start and finish the Causeway; the area, representing the total Causeway work will remain constant.
![]()
There are many different ways of working out the numbers of men involved in working on the Great Pyramid. Already mentioned above are the different manning strategies, and these can have dramatic effects:
The graph above shows the time taken to raise each tier, including quarrying and hauling, but addressing the pyramid only, using two different manning strategies:-
We do not know which, if either, strategy the architects used - it might have been neither, or a combination of the two. However, the building of the calculator raised the need to consider this and many other factors, often neglected.
One thought does militate against the constant annual workforce. As we have seen, the work needed to raise each tier peaks at 1/3rd the height. Using a constant annual workforce, it would appear to an observer that progress was slowing down as the pyramid started to rise. Perhaps this is why some pyramids were never finished, but were abandoned at less than 1/3rd height. Additionally, the builders had no idea how long their project would last, since they could not tell how long the pharaoh was going to live.
For all these reasons it seems sensible to presume that the architects would want to "front-load" the building programme by bringing in as many workers as they could recruit and use early on. This suggestion favours the proportional annual workforce manning strategy, especially for powerful pharaohs like Khufu who could, presumably, command however many men they wanted.
![]()
There are many different ways in which manpower can be calculated - we have just seen the effects of different manning strategies. On top of that, there is the so-called corvée, the annual recruitment of men from all over Egypt to help with pyramid building during the Inundation. The notion goes that the Inundation would render farmers along the Nile redundant until the floods receded; worse, the idle farmers might fall to squabbling. So, able-bodied farmers were recruited each year as a kind of national service, to help build the pyramid.
Nobody is absolutely certain that the corvée really occurred, but it seems like a reasonable idea, and current reserch is showing that the pyramid builders came from the south as well as the north of populated Egypt.
The calculator initially works out Full Time Equivalent Men (FTEM) per tier. One FTEM is one man working full time all year round. If the corvée took place for 3 months each year, then 4 men working for 3 months would, in principle, eat the same food and undertake the same work as one FTEM. And, just to confuse the issue, the manpower could be made up of a core team that did not change each year, plus a variable corvée chosen to make up the proportional anual workforce.
When the priests told Herodotus that up to 100,000 men worked on the Great Pyramid, were they exagerating? Well, not necessarily. The graph shows the result of calculating the number of men needed to construct, not just the Great Pyramid, but the whole complex, employing the proportional manpower strategy, assuming that the corvée was in force, and calculating the numbers of men present on site during the Inundation. Remember, calculations based on physics must necessarily underestimate.
If we then remember, too, that supervision and organization have have not been accounted, and that shiftworking might have been needed to cater for the harsh glare of the July and August sunshine, then we can easily top 60,000 men present on site, albeit only at the start beginning of the project, and only during the Inundation.
![]()
I mentioned at the start that one of the oft-quoted statistics about the Great Pyramid is that the rate of laying stone had to be 89 tonnes per hour, averaged out over 20 years - for the Pyramid alone, excluding the other features in the complex. The graph above shows that to be true. The blue line shows the Cumulative Rate of laying stone, in tonnes per hour, using the proportional manpower strategy. In effect, this tells you what the average would be if you calculated it any any time during the building programme. Right at the end, Tier 202, it does indeed come to 89 tonnes per hour.
Just how misleading this figure can be is shown by the black line, which shows the Mean Rate, also in tonnes per hour, of setting stone tier-by-tier, using proportional manpower. At the start, Tier 1, the figure reaches 264 tonnes per hour, before reducing down to less than 1 tonne per hour by Tier 196. (For the statistically minded, the blue line is effectively the running average.)
![]()
It gets worse. If, in any one year, you can calculate the mean tonnes per hour averaged out over the year, then it seems only reasonable to calculate how much of that was set during the corvée - after all, the point of having the corvée would be to make the greatest building progress.
This graph shows the calculation, using the two manning strategies. With the proportional manpower strategy, the rate of setting stone could exceed 1000 tonnes per hour during the Inundation, but would rapidly tail off towards zero at higher tiers, since this strategy front-loads the work by bringing in many more men up front.
On the other hand, using the constant annual workforce (which could still have a corvée, but would employ the same numbers of men in the corvée each year) the rate of setting stone would not exceed 540 tonnes per hour during the Inundation. However, with no front loading, this constant annual workforce would have to maintain relatively high rates of setting stone at higher tier numbers, exceeding 187 tonnes per hour up to Tier 181. The sudden drop in rate of setting stone is caused by by the fixed workforce having to raise packing and casing stones at this time.
![]()
All this setting of tonnes of stone should raise concerns about ramps. Hollywood films may show shots of simple ramps winding around pyramids, but the amount of stone that ramps would have to carry seems excessive for a simple, temporary structure. If we make the usual assumption, that the average stone weighed 2.5 tonnes, then we can divide the Stone Setting Tonnes per hour from the prevous graph by 2.5 to get the rate of stones being set per hour.
Imagine, if you will, stones being hauled up a ramp incline on sledges. Each team comprised some 25 men, most hauling on ropes, but some levering, some lubricating the sledge runners and at least one supervising. I estimate that one stone plus sledge, with ropes and men, would occupy about 33 linear metres on a ramp, and that there would need to be a space between successive stones and teams of another 33m to allow for each team hauling and resting, hauling and resting...as they climbed.
With this mental picture, the capacity of a single pathway on a single ramp going up a pyramid may be guestimated at some 2 stones per hour continuous. It could be less, it is unlikely to be much more. So, if we had to set stones in place on the pyramid at rates of tens or hundreds per hour, we would need multiple ramps and multiple pathways...
The graph shows the number of simultaneous/parallel paths needed, tier by tier for the two manning strategies. Lower down the pyramid, we are not talking so much about a nice, simple ramp, more a multi-lane highway of enormous proportions. Even if we presume, as some theorists do, that there would be 4 ramps, with 3 taking stone up, and one bringing men, ropes and sledges down, we are still into big numbers per ramp. Taking Tier 100, where the two manning strategy lines coincide, we would need 54 pathways, or 18 pathways per rising ramp. The constant manpower strategy would need some 38 parallel paths at Tier 180, at which height the amount of manoeuvering room has diminished to the point that many pundits doubt the credibility of even simple, single-path ramps.
On top of that, we have not considered the interruptions associated with continually extending the ramps and maintaining them as stone thundered up these supposedly temporary structures. You may have begun to see some cracks forming in the widely accepted ramp theory. You may think that, I couldn't possibly comment...
![]()
It is widely assumed that it took 20 years to build Khufu's Pyramid, and I have used that figure in the calculations above. However, one of the advantages of using a simulation calculator is that you can apply sensitivity checks to less certain figures. In the following analysis, I have combined sensitivity variations to 3 parameters, chosen because they are less certain that other figures used in the simulation:
The graph shows the results of 100 runs, each estimating the build time with different values chosen for the 3 variables from their respective distributions. As the histogram shows, there is a decided spread of estimated years to build the Great Pyramid, with the bulk lying between 15 and 25 years.
|
Mean |
24.56 |
|
Standard Error |
2.16 |
|
Median |
19.90 |
|
Mode |
26.87 |
|
Standard Deviation |
21.56 |
|
Sample Variance |
464.76 |
|
Kurtosis |
32.36 |
|
Skewness |
5.01 |
|
Range |
183.16 |
|
|
|
|
Maximum |
183.16 |
|
Sum |
2455.51 |
|
Count |
100.00 |
The degree of variability is shown in the table, which suggests a more likely build time of some 24 to 25 years, but with a fair degree of uncertainty: it would be unreasonable to read too much into the analysis.
![]()
The Pyramid Calculator is a useful tool and, since it can be applied to any pyramid, it allows comparisons between pyramids to be made with relative ease. However, it does employ simply physics and mathematics, so it produces results which must be interpreted. For instance, it is unlikely that either of the two manning strategies above was employed precisely. Hemon, the architect, may have had other ideas, or his manning strategy might have been a compromise between the proportional and the constant manpower strategies. For all we know, there might have been fluctuations in available manpower according to the Inundation each year...
So, we should use the results from the calculations more as a rough guide than as hard and fast fact. Even then, I don't know about you but I'm a bit sceptical about those pyramid ramps...
![]()